Client: Kermanshah Regional Water Authority | ||
Consultant: Nehad Ab Consulting Engineers Co. | ||
Contractor: 1-Furuzandeh Saz Khorram2- Kar Sazan Saee Gharb |
Project Goals:
_ Supplying Water from the dam through 9 km of transfer channel to 3200 hectares of agricultural land.
_ Executing a net irrigation network of 1570 net ha
_ Construction of four pumping stations with a total capacity of 2.3 m3 / s
Employer: Ministry of Agriculture
Client Consultant: Jamab
EPC: JAMEH RAH JONOOB (Contractor) NEHADAB (Contractor Consultant)
This project is located in the West-Azarbaijan province and on the southern border of the river Aras.
The net land area of the project is 2170 hectares.
In this plan, Irrigation and drainage systems is considered as follows:
Irrigation under pressure at a level of 1100 hectares
Low-pressure irrigation at 835 hectares
Local irrigation at 335 hectares
Underground drainage at 830 hectares.
Employer: Agricultural Ministry
Client Consultant: Nohad Ab Consulting Engineer
EPC: Saman AB JONOOB and Consultant Khazar Ab (Zahak 2 with an area of 8000 hectares)
EPC: JAMEH RAH JONOOB and Kavab Consulting (Zahak 3 with an area of 16,000 hectares)
Client: Lorestan Regional Water Authority | ||
Consultant: Nehad Ab Consulting Engineers Co. | ||
Contractor: Ati Sanat Azna Construction Co. |
Client: Hormozgan Regional Water Authority | ||
Consultant: Nehad Ab Consulting Engineers Co. | ||
Contractor: Jabalbor Construction Co. |
Client: Hormozgan Regional Water Authority | ||
Consultant:Nehad Ab Consulting Engineers Co. | ||
Contractor: Jihadnasr Of Yazad Province |
No. | Name Of Project | Phase | Location | Remarks |
1 | Water Resources Development Project Of The Ghaz River (3500 ha) | 1 | Hormozgan Province | Ended |
2 | The Drainage and Improvement Of Northern Irrigation& Drainage Network Of Minab Dam (2050 ha) | 1, 2 ,3 | Hormozgan Province | Under Construction |
3 | The Study and Design Of Pressure Irrigation Network (4000 ha) | 1, 2 | Fars Province | Ended |
4 | The Irrigation Development Project Of Southern Azna Plain (10,000 ha) | 1 | Lorestan Province | Ended |
5 | The Irrigation and Drainage Studies Of Tashkooeyeh Plain and Socio-economic and exploitation regime Studies | 1, 2, 3 | Hormozgan Province | Under Construction |
6 | The Irrigation and Drainage Network Of Zemkan Dam (3200 ha) | 1 | Kermanshah Province | Under Study |
7 | The Irrigation and Drainage Network Of Kalghan Chai Dam (5000 Hec) and Socio-economic and exploitation regime Studies | 2 | E. Azarbaijan Province | Under Study |
8 | The Irrigation and Drainage Network Of Abolabbas Dam(4000 ha) | 1 | Khouzestan Province | Ended |
9 | The Irrigation and Drainage Network Of Zohreh Dam(4000 ha) | 1 | Khouzestan Province | Ended |
10 | The Irrigation and Drainage Network Of Sardasht Dam (1200 ha) | 1 | Khouzestan Province | Ended |